An attorney for a group of Ahwatukee residents said he filed an $11 million notice of claim against the city of Phoenix on Friday over a 1 million-square-foot data center going up near their homes.
Anthony Ramirez, who represents the Ahwatukee Community Alliance, said the claim is a required first step before suing a local Arizona government.
“A notice of claim is a precursor to a lawsuit,” he explained on KTAR News 92.3 FM’s Outspoken with Bruce & Gaydos.
The eventual lawsuit wants $1 million for lost property values and $10 million for ongoing nuisance conditions, Ramirez said.
Menlo Digital is building the five-building campus on 38 acres near 48th Street and Thistle Landing Drive. Phoenix adopted stricter data center rules in July 2025, but the project received preliminary approvals in 2024, so the new rules don’t apply.
Ramirez challenged that exemption. He said the project’s preliminary site plan expired May 6, and the final site plan was approved later that month.
“How is it exempted from … the new law?” he asked.
Residents want a judge to halt construction.
Arizona Attorney General Kris Mayes called for a statewide pause on new data centers in August and held a town hall on the Ahwatukee project in October.
“We are uncovering every single thing that we can,” Ramirez said.